Illustrative image – not actual.On 15 January 2008, Sutlej Jal Vidyut Nigam (SJVNL) signed a $400 million World Bank loan agreement for building the 412 MW Rampur hydel project in Himachal Pradesh.
The 6x68.66 MW Rampur project is being built on the Sutlej river in Shimla district. The filtered water of the 1,500 MW Nathpa Jhakri project, also built and run by SJVNL, is being used through underground tunnels by the Rampur project to bring down costs of the project.
The state government has 30 per cent equity in the project apart from 12 per cent free power and also shall have additional power allocation as its entitlement under the Gadgil formula as a part of northern grid state. The balance power shall be allocated to all the constituents of the northern grid namely Uttar Pradesh, Uttarakhand, Delhi, Punjab, Haryana, Chandigarh, Rajasthan and Jammu and Kashmir.
The Rampur project is slated to be commissioned by January 2012.
Also See:
WB approves Rs.2,000 crore loan for Rampur power project (12-Apr-07)
Related Links:
Project profile