SJVN starts commercial operations of 60 MW Naitwar Mori hydel projectIllustrative image – not actual.

Power producer SJVN has started commercial operations of its 60 MW Naitwar Mori hydro electric project in Uttarkashi district of Uttarakhand. The company has commissioned both units of 60 MW (2X30MW) Naitwar Mori Hydro Power Station (NMHPS) on River Tons, a major tributary of River Yamuna in the state.

Both the units are now generating commercially after going through testing and successful synchronisation with the national grid. The project will generate 265.5 million units of electricity annually. With this achievement, the installed generation capacity of the company now stands at 2,152 MW.

The power house, which is an underground structure, consists of a diversion structure which is 18.5 mtrs. high and 50 mtrs. long at the top. The power will be evacuated through the 37-km-long 220 kV transmission line from Bainol to Snail. 

From this, water has been diverted into the 4.33-km-long head race tunnel (HRT) with a diameter of 5.6 mtrs. The project has been designed for the discharge of 75.3 cubic mtr per second, while the head is 90.76 mtrs.

← All latest storiesBack to top →