Satluj Jal Vidyut Nigam (SJVN) has established its maiden wind power project at Khirvire in Maharashtra.


The company has successfully established a total of 56 turbines, each with 850 kW capacities for the 47.6-MW project, to generate 85.65 million units of electricity per annum. The contract for installation of turbines was given to the Spanish company Gamesa Wind Turbine. The project which will come up over 51.3 hectares costs around Rs 300 crore.


Work for 22-km long transmission line for connecting the project to the power grid is underway. The grid stabilization for the project is expected to be achieved by October 2013.


Meanwhile the company has signed an MoU with the Bihar Government for setting up a 1,360-MW thermal power plant at Buxar and another with the government of Gujarat for a 5-MW solar power plant in the state.

 

Also, the company has 10 hydro power projects in Uttarakhand, Arunachal Pradesh, Nepal and Bhutan


 