Sixty-three percent work completed on Chandigarh-Kharar flyoverIllustrative image – not actual.

Only sixty-three percent work has been completed on the Rs 369 crore worth Chandigarh-Kharar flyover since the project began in November 2015.

 

As per the National Highways Authority of India (NHAI), the completion of the work includes building of the flyover structure from Khanpur to KFC T-point. It also includes acquiring 15 ha land and demolition of 440 structures out of the 500.

Missing the two deadlines in the past, NHAI has anticipated completion of the flyover by June 2020. The first deadline was December 2018 and the second was March 2020. NHAI is yet to acquire the two ha of land that was delaying the flyover work.

Recently, NHAI received awards of around 12 structures out of 60 in Mundi Kharar from the district administration and have processed the same for payment.