Illustrative image – not actual.The project is being implemented in three packages. Package-IA stretches from 260 km to 275.600 km and 282.450 km to 298.556 km. Package-1B from 275.600 km to 282.450 km and Package-2 from 298.556 km to 338.923 km.
The recent updates on the road project gathered by Projects Today indicate that around 60 percent of the civil work on all the three packages has been completed. The road upgradation from Davangere to Haveri is scheduled for completion in October 2019. In 2017, Ircon International bagged an order worth Rs 1,177 crore to execute the project.
Subsequently, Dilip Buildcon bagged an order worth Rs 360.58 crore for six-laning of Package-2 on engineering, procurement and construction (EPC) mode and Rs 157.23 crore work order for Package-1B. GHV (India) bagged an order for six-laning of Davangere-Haveri Package-1A.