Sixty percent work completed on Purna Barrage-II Irrigation projectIllustrative image – not actual.
The long-delayed irrigation project in Akola district of Maharashtra has reported some progress. The Purna Barrage-II Irrigation project with a capacity of 8.18 million cu mtr is being set up by the Vidarbha Irrigation Development Corporation.

As per information available with Projects Today, the irrigation scheme was taken up in 2008 and in the subsequent year SMS Infrastructure and D Thakkar Constructions joint venture (JV) was appointed as contractor for the project.

In 2010, work commenced on the irrigation project. However, by the end of 2011, the Rs 888.81 crore project was held up due to cost escalation. It was revived after five years in 2016 and during a site visit in 2017, a representative of Projects Today reported that project work was underway with completion re-scheduled for June 2019.

To sustain the ongoing development, in July 2018, the Cabinet Committee on Economic Affairs (CCEA) approved special package for completion of the balance work of Purna Barrage-II project under PMKSY-AIBP.

Following this, the Vidarbha Irrigation Development Corporation decided to complete the project by February 2019, five months ahead of its revised deadline of June 2019. However, during a recent visit to the irrigation project site, Projects Today learnt that around 60 percent work has been completed till date and the completion has been postponed to March 2020.