Illustrative image – not actual.The sixth section of the Jamnagar-Loni pipeline would be commissioned at Nasirabad in Ajmer on 24 December 2000. The remaining two sections of the pipeline are also expected to be commissioned by the end of 2000.
Construction of the pipeline started
in October 2000. With the commissioning of the sixth section, the pipeline
nearly 870 kms of the pipeline will be completed and LPG would has reached
Jaipur through the pipeline.
The 1,230 km long pipeline, which
is estimated to cost Rs.1,250 crore, would have an initial capacity of 1.7
million tonnes per annum. This capacity would be increased to 2.5 million
tonnes by 2011-12.
The pipeline would pass through
the States of Gujarat, Rajasthan, Haryana, Delhi and terminate at Loni in Uttar
Pradesh. The pipeline would be used to transport gas from the Reliance and
Essar refineries at Jamnagar to Indian Oil Corporation and Bharat Petroleum
Corporation and Hindustan Petroleum Corporation.