Six private sector power projects in Andhra Pradesh with a total generation capacity of around 1,500 MW, are expected to achieve financial closure soon. The projects include the Vemagiri, NCC, GVK-II, Gautami, Kondaseema and BPL projects.
The financial closure of these
projects had been delayed as the State had no escrow capacity to offer to
financial institutions (FIs).
FIs have now devised a payment
security mechanism under which there would be concurrent charge of FIs and
banks on the revenues once the projects achieve financial closure. Under the mechanism, the State would turn the
charge on revenue to escrow, one month before the commissioning of the project.
The escrow capacity would be created through power sector reforms during the construction
period. The State Government and the FIs have agreed to sign a memorandum of agreement
under which the State would commit itself to milestones-linked power sector reforms.