Six-laning of Bengaluru-Mysuru highway to kick-off in SeptemberIllustrative image – not actual.

Work on six-laning of Bengaluru-Mysuru national highway will kick-off in September 2018 and the project will be completed in a span of two years. The road project is expected to cut travel time between Bengaluru and Mysuru by 90 minutes. The project will entail an investment of Rs 5,019.62 crore.

The original deadline for completion of the work was three years. According to the plan, the Bengaluru-Mysuru highway development work envisages construction of a main carriageway of six lanes, which will be tolled, and a service road with two lanes on either side of the highway that will not be tolled.

The National Highways Authority of India (NHAI) has divided the work into two packages -- Bengaluru-Nidaghatta (56.2 km) and Nidaghatta-Mysuru (61.1 km).

Around 63 percent of land has been acquired for the project out of the total requirement of 80 percent for the work to commence. The rest of the land will be acquired in the next few days.