Illustrative image – not actual.Delhi-based Himalayan Crest Power's 3 MW hydel power project near Ghiri river in Sirmaur district of Himachal Pradesh is scheduled for completion by July 2008. According to information available with ProjectsToday, around 96 per cent of the project work is completed.
The project to cost Rs.17.47 crore was earlier scheduled for completion by February 2008, but is delayed due to delay in civil works. Shanti Flat & Foundation, Himachal Pradesh is the civil contractor for the project.
Currently, work on the project is underway and after completion the power generated from the proposed power unit will be supplied to HPSEB.