Illustrative image – not actual.National Thermal Power Corporation proposes to achieve financial closure for its 3x660 MW Sipat power project in Chhattisgarh by September 2002. The foundation stone for the project was laid by the Prime Minister, Mr Atal Bihari Vajpayee, on 28 January 2002.
NTPC proposes to set up the first unit within 51 months
from zero date, while the second unit is expected to come up within 12 months
thereafter. The last unit is expected to come up within 12 months of the
completion of the second unit.
In another development, Maharashtra State Electricity
Board has refused to buy 652 MW of power generated from this project following
its non-requirement. Subsequently, the states of Gujarat and Madhya Pradesh
have agreed to buy additional power from the project. A communication in this
regard is awaited from the Centre, after which a decision would be taken in
this connection.
It may be mentioned that according to the original
plan, Maharashtra was to buy 652 MW of power, Gujarat (473 MW), Madhya Pradesh
(258 MW), Goa (24 MW), Dadra Nagar Haveli (8 MW) and Daman & Diu (6 MW).
According to reports, NTPC expects to sell power at
less than Rs.2 per unit, while the cost of generation would be around Rs.4
crore per MW. This low cost is in view of the mega status accorded to the
project by the Centre in December 2001.