Singareni Collieries expects to commission first unit by NovemberIllustrative image – not actual.

Singareni Collieries’ first unit of 2x600 MW power plant is expected to be commissioned by November this year.

 

The plant is coming up in Adilabad district of Telangana. NTPC, BHEL and McNally Bharat are all part of the project.

 

NTPC is the consultant for the project. BHEL is the Boiler-turbine-generator component executing agency, while McNally Bharat is the Balance of Plant (BoP) provider for the coal-fired thermal plant.

 

As per plans, it is proposed to light up the boiler by May 2015. Boiler light up is an important milestone wherein a boiler will be ignited using light diesel oil. This ensures major completion of the boiler works and thereafter the boiler preparation activities such as steam blowing are readied.

 

More project Info:
Coal Based Power (Adilabad) Project