Simhadri STPS expansion: Feasibility study soonIllustrative image – not actual.

National Thermal Power Corporation (NTPC) has drawn up plans to conduct a feasibility study for the expansion of the existing 1,000 MW Simhadri Super Thermal Power Station (STPS) at Visakhapatnam in Andhra Pradesh.

 

According to Mr R C Srivastava, Executive Director (Southern Region), NTPC has plans to add two more coal-based units of 500 MW each to the power station. There are also plans to construct a new coal-based power plant within the Krishnapatnam Port in the state.

 

NTPC has yet to work out the cost of the project and other details. The company is keen on these projects due to their high business potential.

 

Related Stories

 

First unit of Simhadri STPS ready (22 February 2002)

Second unit of Simhadri STPS commissioned (26 August 2002)