Simhadri power project likely to be synchronised within two monthsIllustrative image – not actual.

The first 500 MW unit of National Thermal Power Corporation's 1,000 MW Simhadri power project in Andhra Pradesh is likely to be synchronised by January end / February beginning 2002, two months ahead of schedule. This was stated by general manager of the project, Mr R.C. Srivastava.                                        

 

The power project is estimated to cost Rs.4,035 crore and is being financed through a 70:30 debt equity ratio. The debt component of the project would be funded by Japan Bank for International Co-operation, market borrowing and NTPC’s internal accruals. NTPC has tied up with Mahanadi Coalfields for the 5.04 million tonnes of coal required for the project. The contract for design, manufacturing, engineering, civil construction, erection, testing and commissioning of the project has been awarded to Bharat Heavy Electricals Ltd.