The Centre is advancing the development of the Silchar-Saurashtra East-West Corridor, a 3,576.55 km national highway project crucial for connectivity, commerce, and regional development. The revised completion date for the corridor is set for June 2027.
Over 97 percent of the corridor’s construction is complete. In a written reply to the Rajya Sabha, Union Minister Nitin Gadkari stated that out of the 3,576.55 km corridor, 3,480.62 km has been completed, while the balance 95.93 km is under implementation or in the bidding stage.
The remaining work in West Bengal and Assam faced delays due to pre-construction challenges, including land acquisition, environmental and forest clearances, financial constraints faced by contractors, and force majeure conditions. To address these issues, the government has introduced several initiatives to expedite project execution.
These include streamlining the land acquisition process, revamping the Parivesh Portal for faster forest and environmental clearances, enabling online approvals for General Arrangement Drawings (GAD) of road over bridges (ROB) and road under bridges (RUB) from the Railways, and conducting regular review meetings with stakeholders, including state governments.