The Sikkim Government has decided to withdraw letters of intent issued to private hydroelectricity developers for four hydel projects. The four projects are:

Developer Project Capacity (MW) Location
SSNR Super Power Lingza HEP 99 Tholong Chu, North Sikkim
Costal Energy Rateychu-Bakchuachu HEP 40 Kabi-Tingda, North Sikkim
Shiga Energy Tashiding HEP 88 Rathong-Chu, West Sikkim
SMEC International Ting-Ting HEP 90 Rathong-Chu, West Sikkim

It is learnt that, the decision to withdraw the letters of intent was because of non-performance of activities as per the agreement signed between the Government and the private parties and non-compliance of milestones as per letter of intent and because of technical flaws in the pre-feasibility reports submitted.