Signature Bridge to open in October 2018Illustrative image – not actual.

The Signature Bridge, being constructed across the Yamuna River in Wazirabad, Delhi, is likely to be thrown open to public in October 2018. The project aims to reduce travel time between north and northeast Delhi by improving traffic movement on the Ring Road.

The bridge will be the nation’s first asymmetrical cable-stayed bridge, and will be 675 mtr long and 35.2 mtr wide.

Delhi Chief Minister Arvind Kejriwal witnessed the installation of the final pylon on the 154 mtr high bridge. The government will release the final installment of funds required to complete the project in June 2018.

The state government has so far released Rs 1,344 crore towards the development of the project. The cost has escalated from the initial amount of Rs 887 crore.

The government is likely to revise the cost to Rs 1,511 crore after the Central Public Works Department (CPWD), from which the PWD had sought expert opinions on cost escalation, has justified Rs 1,511 crore.

However, the Delhi Tourism and Transportation Development Corporation (DTTDC), which is executing the project, had sought Rs 1,574 crore. The proposal is likely to be put forth in the Expenditure and Finance Committee meeting following which it will be put up for the cabinet nod.

Once the funds are released, the construction of the bridge is likely to pick up pace. Around 95 percent work is complete.

The project was conceptualised in 2004 and in 2007 it received the cabinet nod. The first deadline was fixed ahead of the Commonwealth Games held in 2010, and later revised to 2013.

 