Shree Renuka Sugars to expand distillery capacityIllustrative image – not actual.

Shree Renuka Sugars in a board meeting held on April 12, 2006 approved the following:

  • A proposal for acquisition of a 23 MW power plant from Sarita Sugars Ltd at a cost of Rs.39.72 crore and relocating the same to Karnataka.
  • A proposal for addition of 60 klpd and 150 klpd distillery capacity at two locations in Maharashtra and Karnataka at a cost of Rs.50 crore. These distilleries are scheduled to begin operations in December 2006 and March 2007 respectively.
  • A proposal for the setting up of cogeneration capacity of 15 MW in Karnataka with a capital outlay of Rs.30 crore.

The board also proposed to raise financial through the issuance of foreign equity.

With these proposed additions and projects announced earlier, the company's total distillery capacity would rise to 450 klpd during the 2006-07 sugar season. Likewise, cogeneration capacity would stand enhanced to 103.5 MW.