Illustrative image – not actual.Shree Cement is setting up a new unit with a capacity of six million tpa at Khapradih village, Simga taluka in Raipur district of Chhattisgarh. The unit will be set up on 531.12 ha of land. The water of 3,000 kpd will be sourced from ground. The Ministry of Environment, Forest & Climate Change (MoEF&CC) has already accorded environmental clearance (EC) to the project.
The cement unit will be supported by a clinker unit with a capacity of 5.2 million tpa, coal-based power unit of 25 MW, WHRB power unit of 30 MW, synthetic gypsum of 65 tph and DG sets of 2,000 kVA.
Shree Cement acquired land and commenced work on the clinker unit in 2016. The unit was ready in a year by 2017. Construction work on WHRB power unit is underway from past two years. As conveyed to the Projects Today team, the promoter is hopeful of completing WHRB power unit soon by November 2018. Further, project work on cement and the remaining units is yet to commence.