Shree Cement’s plant in Pune to commence operations in September 2021Illustrative image – not actual.

The western Indian foray of Shree Cement had been delayed due to COVID-19 disruptions, but the company expects to commence commercial production from September 2021.

The completion of a clinker grinding unit of three million tpa at Patas in Pune district of Maharashtra got delayed by a year because of COVID-19 and the right of way issues. Investment in the plant, spread across 65.7 acre, was over Rs 600 crore and will get clinker from its group plant in Karnataka.

However, during 2020-21, the company had commissioned commercial operations of a clinker grinding unit having capacity of three million tpa at Athagarh Tehsil in Cuttack district of Odisha.

The company has about 43 million tonne capacity from four integrated plants and nine grinding units in a total of nine states.

The company is setting up upto 12,000 tpd brownfield clinkerisation unit at village Khapradih in Baloda Bazar district of Chhattisgarh. The project activities are running on track and the project is likely to be completed in H1/FY23.

The cement major was eyeing for 80 million tonne capacity by 2030.

 