The
State Cabinet of Andhra Pradesh, on 11 December 2000, approved the
recommendations of the task force on Power for scaling up the capacities of eight
short gestation power projects in the State.
In
1996-97, the State government had cleared eight fast track projects with a
combined capacity of 1800 MW. All these projects were based on naphtha as fuel.
Of these projects, only the 360 MW Lanco Power Project located at Kondapalli
near Vijaywada has been commissioned.
Further,
the State government is keen on these projects to use natural gas as fuel, in
view of the high international prices of naphtha. The government estimates that
these power projects would be able to generate power at a tariff of around
Rs.1.80 per Kwh.
To
boost the progress of these projects, the government is also planning to
arrange for natural gas supplies, initially for a capacity of 1,500 MW.
