The Ministry of Road Transport & Highways has restructured the Shivpuri-Dewas road project in Madhya Pradesh and awarded into three packages, i.e. (i) Shivpuri-Guna; (ii) Guna-Biaora; and (iii) Biaora-Dewas.
Shivpuri-Guna Section (236.00 km to 332.100 km) has been awarded to IRCON International on 31 March 2015 with total project cost of Rs 830.36 crore and the work is likely to be completed by June 2018.
Guna-Biaora Section (332.100 km to 426.100 km) has been awarded to Dilip Buildcon on 29 June 2015 with total project cost of Rs 1,012.90 crore and the work is likely to be completed by September 2018.
Biaora-Dewas Section (426.100 km to 566.450 km) has been awarded to Oriental Structural Engineers on 29 June 2015 with total project cost of Rs 1,583.79 crore and the work is likely to be completed by August 2018.
Earlier, Shivpuri-Dewas section of NH-3 was awarded to GVK Transport Networks Hyderabad on Build-Operate-Transfer (BOT) (toll) basis with total project cost of Rs 2,815 crore.
However, the project was terminated by National Highways Authority of India (NHAI) on 7 May 2014 due to non-achievement of financial closure by the concessionaire.