Shiradi Ghat to be thrown open by June 2018Illustrative image – not actual.

The second stretch of Shiradi Ghat in Karnataka is likely to be thrown open to traffic by 15 June 2018. The first stretch of 13 km of Shiradi Ghat between Maranahalli and Kempu Hole Guest House was concreted in August 2015.

The work under Package-2 of Shiradi Ghat reconstruction commenced on 20 January 2018 after the stretch was closed for traffic.

With the reconstruction, NH-75 in the entire Shiradi Ghat stretch, including the one between Gundya and Adda Hole, will have a uniform width of 8.5 mtr and thickness of 45 cm. The road width varied between six mtr and seven mtr earlier.

The laying of concrete is expected to be completed by the end of May 2018. The contractor will also take up ancillary works to give finishing touch to the road while the concrete work gets completed.

The contractor is likely to complete the work in six months as against seven months taken for Package-1.