Illustrative image – not actual.The Shiradi Ghat in Karnataka was opened for traffic on 15 July 2018. The concreted remaining portion of the ghat was inaugurated Nalin Kumar Kateel, MP for Dakshina Kannada, and Ministers H D Revanna and U T Khader.
Of the 37 km of the ghat stretch, 26 km was proposed for concretisation in 2014. The stretch between Heggadde and Kempu Hole Guest House in Hassan district was concreted between January 2015 and August 2015. Concreting of the remaining 13 km started on 15 January 2018.
The contractor, Ocean Constructions, completed the work in six months instead of the scheduled deadline of 18 months. Some ancillary safety works are pending, but they are expected to be completed in a fortnight.
The same contractor had executed Phase-I of the roadwork. The contractor has also been urged to take up the proposed Shiradi Green Bypass Project (between Marenahalli in Hassan district and Gundiya in Dakshina Kannada district). A detailed project report (DPR) worth Rs 12,500 crore has already been completed. The project will be implemented on build-operate-transfer mode.