Shipping ministry clears NMDP final draftIllustrative image – not actual.

The Union Ministry of Shipping (MoS) has approved the final draft of the National Maritime Development Programme (NMDP), it is learnt.

The programme, to be executed till 2011-12, comprises two phases of 180 projects and 96 projects, respectively and will be sent to the Infrastructure Committee, headed by the Prime Minister, Dr. Manmohan Singh for further approval.

Major projects under the programme include deepening of channels, development of berths, replacement of equipment and port connectivity.

National Maritime Development Programme (NMDP) for the country plans an investment of Rs.1,00,339 crore to be spent in 387 identified projects in port and shipping sector spread over 20 years.

The total investment includes Rs.55,804 crore for the port sector during the next six years to be funded through public private partnership (PPP). This will enhance the aggregate cargo handling capacity of 12 major ports to 820 million tpa by 2011-12 from the existing 397.5 million tpa.

For this, the NMDP seeks to implement

  • Seventy Six projects for construction of berths and jetties
  • Twenty Five projects that would help deepen port channels
  • Fifty Two projects that include procurement, replacement and upgradation of port equipment
  • Forty Five projects aimed at improving port connectivity to the hinterland
  • Seventy Eight other related schemes dedicated to improve storage capacities, internal circulation systems.

NMDP is also included in the programme with an investment of Rs.44, 535 crore for development of shipping and inland water transport (IWT) through budgetary support and internal and external budgetary resources over a 20-year period (up to 2024-25).

This includes 111 projects on activities such as vessel acquisition by Shipping Corporation of India, maritime training activities, setting up of navigational aids and shipyards and promoting inland water transport, amongst others.

Public investment will be primarily for common user infrastructure facilities such as deepening of port channels, construction of breakwaters, internal circulation systems of cargo within the ports, rail and road connectivity, among others.

Private investments are planned in areas where operations are primarily commercial in nature such as construction, management and operation of berths and terminal.

Port Sector
From the activities envisaged for ports, 180 projects requiring an estimated investment of Rs.31,971 crore will be taken up during Phase-I.

Aggregate capacity in the major ports at the end of Phase-I activities is expected to be 652.30 million tpa and Phase-II includes projects to be taken up by 2011-12.

The Phase-I activities is to be funded by

  • Budgetary support of Rs.1,350 crore,
  • The Rs.8,991crore to be raised by the major ports from their internal resources,
  • The Rs.19,112 crore of private investment and
  • The Rs.2,518 crore from the National Highways Authority of India, Railways and other organisations.

The major activities listed under first phase include the third container terminal and JNPT, offshore container berths at Mumbai and container terminals at Kandla and Chennai, amongst other port connectivity projects.

Shipping/IWT Sector:
Out of the total investment under shipping/IWT sector, Rs.13,775 crore is expected to accrue from budgetary support and Rs.17,460 crore is expected to accrue from the internal and extra budgetary resources by 2024-25.