Illustrative image – not actual.Shilchar Technologies has announced that its third manufacturing unit in Gavasad, Vadodara, is on track for commissioning by April 2027.
The new facility will add 6,500 MVA of annual capacity, nearly doubling the company's total output from 7,500 MVA to 14,000 MVA. Currently, civil foundation work is complete, and construction of the pre-engineered building (PEB) is underway, with all major production machinery already ordered. This expansion marks a significant evolution for the company. While Shilchar currently focuses on transformers up to 50 MVA and 132kV, the new unit could elevate their product line to the 220kV class. The Gavasad site has seen consistent growth, rising from an initial 1,000 MVA to its current level following expansions in 2018 and 2024. Notably, the company has secured additional land that could potentially double capacity again beyond 14,000 MVA in the future.
For the ongoing financial year (FY27), Shilchar expects 100 percent utilisation of its existing 7,500 MVA capacity, a significant jump from the 78 percent utilisation rate recorded in previous years.