The Board of Approvals, Union Ministry of Commerce, has on 20 November 2009, formally notified Technopark Phase III at Thiruvananthapuram and Technopark-Kollam as SEZs.

Technopark Phase III is being developed over 92 acre. Construction of a building with 1 million sq ft built-up area has already commenced.

Land in the park is likely to be given away mostly to IT/ITeS companies and infrastructure development companies. Other infrastructural facilities such as 110 kV sub-station and water supply system are already complete and work on sewage treatment plant, canal embankment, approach road, internal roads and bridge works are in progress.

Technopark-Kollam is to be developed on 40 acre at Kundara on the banks of the Ashtamudi Lake. When completed, this project is expected to have 2 million sq ft of built-up space. Phase I of Technopark-Kollam is expected to be ready for occupation by early 2011.