Illustrative image – not actual.Three underground sewerage projects worth Rs 1,128.32 crore in Andhra Pradesh are expected to be completed by 2018.
The Public Health & Municipal Engineering Dept, Andhra Pradesh, awarded three underground sewerage scheme projects to contractors in 2016.
Shapoorji Pallonji was awarded a contract worth Rs 777.04 crore for implementation of an underground sewerage scheme with a capacity of 37 MLD in Guntur.
Maruti Construction, Vishakhapatnam, was awarded a contract for development of an RCC major drain from Innispeta to STP for Rajamahendravaram Municipal Corporation in East Godavari district, under Pushkaram Grant Works. The estimated value of this project is Rs 6.10 crore.
Larsen & Toubro was awarded a contract worth Rs 345.18 crore for implementation of a storm water drainage scheme with a capacity of 26.8 MLD at Vijayawada city in Krishna district.
Around 70 percent of work on the RCC major drain has been completed at Rajamahendravaram, while work on the remaining two projects is underway.
Work on the RCC major drain is scheduled to be completed in August 2017, while work for Vijayawada city and Guntur Municipal Corporation will be completed by June and December 2018 respectively.
The Public Health & Municipal Engineering Dept, Andhra Pradesh, awarded three underground sewerage scheme projects to contractors in 2016.
Shapoorji Pallonji was awarded a contract worth Rs 777.04 crore for implementation of an underground sewerage scheme with a capacity of 37 MLD in Guntur.
Maruti Construction, Vishakhapatnam, was awarded a contract for development of an RCC major drain from Innispeta to STP for Rajamahendravaram Municipal Corporation in East Godavari district, under Pushkaram Grant Works. The estimated value of this project is Rs 6.10 crore.
Larsen & Toubro was awarded a contract worth Rs 345.18 crore for implementation of a storm water drainage scheme with a capacity of 26.8 MLD at Vijayawada city in Krishna district.
Around 70 percent of work on the RCC major drain has been completed at Rajamahendravaram, while work on the remaining two projects is underway.
Work on the RCC major drain is scheduled to be completed in August 2017, while work for Vijayawada city and Guntur Municipal Corporation will be completed by June and December 2018 respectively.