Seven companies submit pre-qualification bids for Central Vista projectIllustrative image – not actual.
Seven companies have submitted pre-qualification bids for the Central Vista redevelopment project in Delhi.
 
Tata Projects, Larsen & Toubro, ITD Cementation India, NCC, Shapoorji Pallonji and Co, Uttar Pradesh Rajkiya Nirman Nigam and PSP Projects had submitted their bids.
 
As part of the Central Vista redevelopment project, construction of the new Parliament building, close to the existing one, is expected to be completed in 21 months at an estimated cost of Rs 889 crore.
 
The Central Public Works Department (CPWD), a prime construction agency of the Central government, stated that the new building will be constructed at plot number 118 of the Parliament House Estate.
 
While developmental work will be looked after by CPWD, in 2019 it chose HCP Design, Planning & Management (HCPDPM), an Ahmedabad-based architecture firm, as the project consultant. After revisiting the masterplan for the central Delhi area, HCPDPM is now responsible for coming up with new designs and/or alterations required for the project.
 
The proposed new Parliament building will be a reinforced cement concrete framed structure. The plinth of the building will match with the plinth of the existing building, which is approximately 1.8 mtr above ground level.
 
The total plinth area of the proposed building is approximately 65,000 sq mtr including the basement area of approximately 16,921 sq mtr. The building will be ground-plus-two-storey with one basement.
 
Designed to accommodate over 1,000 members of Parliaments, in addition to private chambers for all MPs, the building will have offices for ministers and secretaries.  
 
The existing Parliament building will continue to function during the entire period of execution of the project. The existing temporary structures on plot number 118 will be demolished before construction starts.
 
The existing boundary wall also needs to be demolished and a new one will be constructed as per the design and drawings provided by the department.
 
The cost of the project has gone up due to additional infrastructure requirements and an increase in the size of various facilities. The government has set a 2022 deadline to complete the new building.