Illustrative image – not actual.Five Indian companies and others from USA, Korea, Netherlands and Belgium have submitted their bids for carrying out dredging works of the remaining three phases of the Rs.2,427 crore Sethusamudram Ship Canal, according to Union minister for shipping and road transport, Mr T R Baalu.
The pre-bid qualification for the remaining three phases -- one on Palk Strait and two on Adam's Bridge -- will be completed by 15 September 2005. Physical work is likely to commence by 15 November 2005.
Dredging Corporation of India has already begun work for a length of 13.57 km in the Palk Strait area, on 2 July 2005, the day of project inauguration. DCI was appointed contractor for the first leg of the dredging work on nomination basis.