The Andhra Pradesh Government has issued orders withdrawing the MoU it had signed with Moser Baer Infrastructures Developers.
In 2008, the state government had signed the MoU with Moser Baer for setting up a 100-acre manufacturing SEZ. The MoU has been cancelled as the company did not pay the lease premium despite notices sent by Andhra Pradesh Industrial Infrastructure Corporation.
As per the agreement, the company was to pay a rental of Rs 15 lakh an acre for a period of 66 years to develop the project in two phases. The Phase I was to have investments of $200 million (approx Rs 880 crore) within two years after signing the pact. Under this phase, the company was to make solid state memory devices such as pen drives. The company was required to invest $300 million (approx Rs 1,320 crore) under the Phase II for manufacturing products such as semiconductor optical storage media and photovoltaic thin film technology.
The company had sought an extension of two years to take up the project.