Senbo & ITD emerges L1 bidder for underground works of Kolkata Metro Barasat Line’sIllustrative image – not actual.
Senbo Engineering and ITD Cementation India has emerged as the lowest (L1) bidders for 3.6 km underground extension of Kolkata Metro’s 6.87 km Line-4 from Kolkata Airport (Bimanbandar) to New Barrackpore. 
 
The underground section of 18.13 km Yellow Line will help linking Noapara with the suburb of Barasat in north-east Kolkata. The construction work for the project will be carried out using cut and cover method and no TBMs will be used.  
 
The alignment will primarily run along Netaji Subhas Chandra Bose International Airport (NSCBI)’s land and includes two new stations at Birati and New Barrackpore. 
 
Metro Railway Kolkata had invited bids in January 2022 in three packages including two packages for tunneling works and one for subway works linking the airport’s terminal.