Semi-high speed rail line project worth Rs 56,443 cr gets big pushIllustrative image – not actual.
The government of Kerala has expedited steps for the 531.45 km semi-high-speed rail line from Thiruvananthapuram to Kasaragod by seeking aid from the Japan International Cooperation Agency (JICA).

The project has been found to be ‘feasible and economically viable’ by the government and the detailed project report (DPR) for the Rs 56,443 crore project is also being prepared.

With the feasibility report, alignment, and revenue model from the Paris-based consulting firm Systra has reached the government for approval. The Kerala Rail Development Corporation (KRDCL) has commenced steps to go forward with the project.

The government has approached the country office of the JICA through the Union Department of Economic Affairs to secure Rs 34,000 crore as loan for the project to be executed on cost-sharing basis by the state government and Indian Railways.

Systra, general consultant for the KRDCL, has suggested in the feasibility report that the state government and Indian Railways have to mobilise Rs 10,000 crore each. The state government, in addition, will have to bear the cost of acquiring 1,226 ha in 11 districts.

The aim is to secure assistance from the JICA, the governmental agency that coordinates official development assistance for the government of Japan, through the DEA at least during 2021.

The feasibility report needs the approval of the KRDCL board, state government, and Indian Railways. The KRDCL may be ready with the DPR by October 2019, the work on the rail lines will begin in 2020.

A fresh traffic study, field survey, soil investigation, and environment impact assessment will have to be carried out. Tenders have been floated for carrying out the field survey by Light Detection and Ranging (LIDAR). The bids for carrying out soil investigation will be floated soon.