Section of Mahabubnagar-Munirabad rail project advances fastIllustrative image – not actual.

A crucial stretch of the Mahabubnagar-Munirabad New Railway Line Project is progressing fast. The 66 km Devarakadra-Krishna stretch will entail an investment of Rs 372.09 crore.

The balance work between Jaklair-Krishna is under progress. Out of 866 acre of land required for construction, 734 acres of land has been acquired by the state government and handed over to the Railways. The balance 132 acre in Mahabubnagar district is in the process of handing over to the Railways. The project is included in the Prime Minister Monitoring Group (PMG) and a constant review on the progress is being held on a periodical basis.

The remaining portion of the project between Jaklair-Krishna is going on rapid pace and targeted to be completed by 2019-20.

The portion falls under South Central Railway Jurisdiction which covers rural belt of Telangana region, and the remaining portion belongs to South Western Railway serving the Karnataka area.

The stretch is part of the new railway line between Mahabubnagar-Munirabad which was sanctioned in the year 1997-98 for a distance of 247 km at an estimated cost of Rs 1,723 crore. Devarakadra-Jaklair line stretching over 29 km was completed and dedicated to the nation by Union Minister of Railways Piyush Goyal on 25 March 2017 by flagging off passenger train service between Devarakadra and Jaklair. An amount of Rs 499 crore has been from FY15 till November 2018. The budget allocation for 2018-19 is 175 crore.

The Mahbubnagar-Munirabad new line will significantly reduce distance between Hyderabad to Hubbali and Goa, to the extent of 102 km as compared to the present route.

Three major bridges, 82 minor bridges, five road overbridges and 27 road underbridges are being constructed in the section as a part of the new line.

 