Illustrative image – not actual.Prime Minister, Atal Bihari Vajpayee,
will inaugurate the second section of the Delhi Metro Rail Project -- a 4.5 km
link between Tis Hazari and Trinagar -- on 2 October 2003. With this, the 8.3
km Shahdara-Tis Hazari line, operational since December 2002, will get extended
to 12.8 km. The total length of the Delhi Metro Rail is 28 km.
The Tis Hazari-Trinagar section,
costing Rs.270 crore, forms part of Line 1 (Shahdara to Barwala) being taken up
in the first phase of the project. There are three lines being taken up in the
first phase, the other two being the
Connaught Place-Dwarka corridor (Line 2) and the Central Secretariat-Delhi
University corridor (Line 3).
With four stations, the section
would serve densely-populated parts of the capital. Another 8.5 km section,
between Trinagar and Rithala of this line, would become operational by March
2004.
Around 98 per cent of the civil
works and about 80 per cent of the electrical work on the section had been
completed, DMRC officials said. The deadline for completion of this section was
September 2003. The entire 66 km Phase I of the metro project is to be
completed by September 2005.