Second lake tapping at Koyna dam completedIllustrative image – not actual.

The second lake tapping aimed at facilitating smooth functioning of the Koyna dam in Maharashtra was successfully conducted in the dam’s reservoir in Patan taluka on 25 April 2012.

The six inch thick rock under the water of the dam’s reservoir was blasted on the boundary of Manainagar and Irgaon villages. The second lake tapping was completed at a cost of Rs 528 crore. The project is expected to end water and electricity woes of the state. The exercise will enable generation of additional 1,000 MW of electricity at Koyna Dam, which currently has an installed capacity of 1,960 MW and help irrigation schemes of the drought areas of Sangli and Satara namely Takari, Tembu and Mhaishal. With this, Stage IV of Koyna will operate its turbines at a higher rate even when reservoir's water level is depleted to 630 mtrs and meet the power demand during peak hours. The Water Resources Department carried out the second lake tapping.

The completion of the second lake tapping has also shifted focus to stage V that need environmental clearance from the Central Government.

Lake tapping is piercing the lake from the bottom by blasting a rock plug, thus enabling the flow of water into a tunnel. For this lake tapping, a 4.5 km long tunnel having a dia of 9.5 mtrs has been constructed.
 

← All latest storiesBack to top →