Illustrative image – not actual.The Solar Energy Corporation of India (SECI) has invited bids for setting up 1,200 MW ISTS-connected wind power projects in India under tariff-based competitive bidding. The last date for submission of bids is 6 July 2021.
The projects will be set up on a build-own-operate basis for an aggregate capacity of 1,200 MW and SECI will enter into a power purchase agreement with the successful bidders selected for a period of 25 years.
The power procured by SECI from these projects will be sold to the discoms of Madhya Pradesh. The discoms will procure power through Madhya Pradesh Power Management Company which is the authorised representative for signing the power sale agreement.
The bidder will have to submit a single bid offering at a minimum capacity of 50 MW and a maximum of 1,200 MW and the projects have to be quoted in multiples of 10 MW only.
A project of 100 MW or less capacity can be commissioned in a maximum of two parts and those with more than 100 MW capacity should be commissioned in parts of at least 50 MW each, with last part being the balance capacity.
The Scheduled Commissioning Date (SCD) for the commissioning of the full capacity of the project is 18 months from the effective date of the PPA. The maximum time period allowed for commissioning full project capacity with applicable liquidated damages is 270 days from the SCD.
The projects will be set up on a build-own-operate basis for an aggregate capacity of 1,200 MW and SECI will enter into a power purchase agreement with the successful bidders selected for a period of 25 years.
The power procured by SECI from these projects will be sold to the discoms of Madhya Pradesh. The discoms will procure power through Madhya Pradesh Power Management Company which is the authorised representative for signing the power sale agreement.
The bidder will have to submit a single bid offering at a minimum capacity of 50 MW and a maximum of 1,200 MW and the projects have to be quoted in multiples of 10 MW only.
A project of 100 MW or less capacity can be commissioned in a maximum of two parts and those with more than 100 MW capacity should be commissioned in parts of at least 50 MW each, with last part being the balance capacity.
The Scheduled Commissioning Date (SCD) for the commissioning of the full capacity of the project is 18 months from the effective date of the PPA. The maximum time period allowed for commissioning full project capacity with applicable liquidated damages is 270 days from the SCD.