SECI eases norms for 10 GW solar auctions linked to manufacturingIllustrative image – not actual.
The Solar Energy Corporation of India (SECI) has eased a few norms for firms potentially participating in 10 GW solar auctions linked to manufacturing. This is being done following multiple postponements for the bid submission dates.

As per new amendments, the amount of bank guarantee to be submitted by developers has been reduced by almost 25 percent to Rs 466 crore. The ceiling tariff for auctions has also been cut down to Rs 2.75 per unit, instead of the Rs 2.93 per unit set earlier.

To boost solar manufacturing, the government had introduced the manufacturing-linked solar scheme, where developers will be provided with assured power purchase agreements (PPA) against the capacity of solar module manufacturing plant they set up in the country.

As much as three GW of cumulative annual solar manufacturing units are seen to be set up over three years, resulting in 10 GW of new generating capacities.