Illustrative image – not actual.A memorandum of understanding (MoU) has been inked between Singareni Collieries (SCCL) and the South Central Railway (SCR) for Bhadrachalam Road-Sattupalli Rail Line project in the state of Telangana.
SCCL handed over a cheque worth Rs 200 crore to SCR towards completion of the 54.10 km rail line project towards the end of 2020.
SCCL has so far paid upto Rs 365 crore of the Rs 618.55 crore revised cost estimates for additional works, taking the total project cost to Rs 927.94 crore from the earlier cost of Rs 704 crore.
The share of the Railways is Rs 309.39 crore for the line which will be used for environment-friendly transport of coal from open cast mines around Sattupalli.
The project was cleared by the Railway Board in March, 2017, and SCCL had then deposited an amount of Rs 156.38 crore as per the initial cost estimate.
Around 90 percent of the 353 ha of land acquisition for the project has already been completed with support of the Telangana government.
There are around 10 major bridges along the route covering Bhadradri-Kothagudem and Khammam districts, of which work on seven bridges is underway.
Apart from this, another 40 minor bridges, eight road-overbridges, 34 road-under-bridges and three crossing stations have to be constructed.
Once completed, the railway line will facilitate moving up to nine million tonne of coal to Bhadrachalam for feeding power plants like Kothagudem thermal power station and Kondapalli thermal power station.
The Railways would get a revenue of about Rs 160 crore per annum.
SCCL handed over a cheque worth Rs 200 crore to SCR towards completion of the 54.10 km rail line project towards the end of 2020.
SCCL has so far paid upto Rs 365 crore of the Rs 618.55 crore revised cost estimates for additional works, taking the total project cost to Rs 927.94 crore from the earlier cost of Rs 704 crore.
The share of the Railways is Rs 309.39 crore for the line which will be used for environment-friendly transport of coal from open cast mines around Sattupalli.
The project was cleared by the Railway Board in March, 2017, and SCCL had then deposited an amount of Rs 156.38 crore as per the initial cost estimate.
Around 90 percent of the 353 ha of land acquisition for the project has already been completed with support of the Telangana government.
There are around 10 major bridges along the route covering Bhadradri-Kothagudem and Khammam districts, of which work on seven bridges is underway.
Apart from this, another 40 minor bridges, eight road-overbridges, 34 road-under-bridges and three crossing stations have to be constructed.
Once completed, the railway line will facilitate moving up to nine million tonne of coal to Bhadrachalam for feeding power plants like Kothagudem thermal power station and Kondapalli thermal power station.
The Railways would get a revenue of about Rs 160 crore per annum.