Illustrative image – not actual.The Supreme Court (SC) has suspended Punjab and Haryana High Court (HHC) order directing the NHAI to take over Panipat-Jalandhar highway project as the builder had failed to complete it within the scheduled time.
The concessionaire for the 291-km Panipat-Jalandhar highway project, Soma Isolux NH-1Tollway was likely to complete the project by 2011, and going by the undertaking given to the high court, the project should have been completed by 2012.
The developer had expressed difficulties in completing the remaining 40-km stretch of the Panipat-Jalandhar NH project without shifting the toll plaza. Currently, the toll plaza is located at 146 km on the highway but the project concessionaire wants it to be shifted to 110 km at Karnal.
The SC directed NHAI to consult the central government if shifting of the toll plaza from its existing location could be permitted, and if not cite the reason why the toll plaza could not be shifted to the site being sought by it.