Illustrative image – not actual.The Supreme Court (SC) ordered maintenance of status quo till 5 January 2008 to consider the bids of Zoom Developers for the construction of the proposed Vizhinjam Deepwater Container Transshipment Terminal. The SC order was issued on 17 December 2008.
On 5 December 2008, the High Court had ordered that until a decision was taken on the proposal of the Mumbai-based Zoom Developers, the proceedings initiated for awarding the contract to Lanco Kondapalli Power Ltd., Hyderabad, be kept in abeyance. It also ordered that if the bids submitted by Zoom Developers were found to be better, the decision to award the contract to the Hyderabad-based company be cancelled.
The High Court order has issued the order while setting aside a decision of the Kerala government and Vizhinjam International Seaport Ltd. to reject the technical and financial bids submitted by Zoom Developers for the port project. The High Court had pointed out that the Kerala was not justified in excluding the appellant from the zone of consideration during the bid evaluation stage on the ground that a new partner was added at a later stage.
Also See:
Lanco-led consortium's Kerala port project lands in trouble(05-Dec-08)