Illustrative image – not actual.State Bank of India (SBI) has raised objections to the Gujarat Electricity Board (GEB) granting escrow cover for three power projects, viz. Gujarat State Energy Corporation’s 156 MW Hazira power project, Reliance Industries’ 500 MW Jamanagar power project and Gujarat Mineral Development Corporation’s 250 MW Akrimota power project.
Though reasons for SBI’s objections are not clear, the same could be attributed to GEB’s poor financial position. Reportedly, GEB has Rs.800 crore overheads. Another reason for the objections could be that though the power purchase agreement entered into with the project promoters, includes a three-tier security mechanism, i.e. letters of credit (LCs), an escrow cover and government guarantee, GEB has yet to issue the LCs.
SBI’s objections may delay the Jamnagar project’s financial closure and stall the completion of the other two projects, which have already commenced work.