SBI Caps to tie up debt for Maithon PowerIllustrative image – not actual.

Maithon Power Ltd (MPL) has appointed SBI Caps as principal arranger of debt for its 1,000 MW coal-based power project. The Rs.5,752 crore project is proposed to be set up in Jharkhand.

 

Apart from SBI Caps, IDBI and ICICI were in the race for bagging the mandate.

 

The project is likely to have a debt-equity ratio of 70:30. The equity would be shared equally between Damodar Valley Corporation (DVC) and BSES, the promoters of MPL.

 

The foundation stone for the project was laid almost 18 months ago, but no progress has been made owing to land acquisition delays. MPL needs 1,200 acres at Nirsa in Dhanbad district, but has failed to acquire any land so far. The first phase is scheduled to be commissioned by September 2005.

 

The Maithon project is one of eight projects that DVC plans to undertake in the 10th and 11th Plan periods, at a total cost of Rs.19,000 crore. DVC will seek budgetary support to part-finance these projects, which would increase its capacity by 2,780 MW. DVC’s existing capacity is 2,761.5 MW.

← All latest storiesBack to top →