Sadbhav Bhavnagar Highway (SBHPL) and Sadbhav Una Highway (SUHPL), wholly owned subsidiaries of Sadbhav Infrastructure Project have secured financial closure for two NHAI projects in the state of Gujarat.
SBHPL secured financial closure for four laning of Bhavnagar to Talaja section (Package-1) of NH-8E from 7.09 km (design chainage 6.95 km) to 53.59 km (design chainage 54.99 km) in Gujarat, on Hybrid Annuity mode, under NHDP Phase-IV.
The cost of the bidding project is Rs 819 crore, of which the term loan will be Rs 393.12 crore, while NHAI will fund Rs 327.60 crore, and the remaining amount of Rs 98.28 crore will be contributed by the company.
SUHPL secured financial closure for four laning of Una to Kodinar section (Package-V) of NH-8E from 180.48 km (design chainage 181.45 km) to 221.61 km (design chainage km 222.40 km) in Gujarat, on Hybrid Annuity mode, under NHDP Phase-IV.
The cost of the bidding project is Rs 623 crore, of which the term loan will be Rs 299.04 crore, while NHAI will fund Rs 249.20 crore, and the remaining amount of Rs 74.76 crore will be contributed by the company.
The financial closure was completed within the stipulated time in accordance with the Concession Agreement executed with NHAI, dated 19 July, 2016.
The construction period for both the projects is 910 days, while the appointed date for both the projects is expected soon.
Both the projects have an operational period of 15 years from CoD.