Illustrative image – not actual.Nagpur-based Sanvijay Rolling & Engineering plans to set up a 2x20 MW captive power plant at MIDC Butibori in Nagpur district of Maharashtra. The project will come up at its existing location that houses a mini steel plant and two rolling mills.
The DPR will be ready by mid-December 2006. Phase I, envisaging one power unit of 20 MW, is likely to be commissioned by July 2008, with an investment of Rs.98 crore. Work on Phase II will begin thereafter.
The company had plans of setting up a sponge iron unit at Bhadravati in Chandrapur district in the same state. The project has been put on hold in favour of pursuing the captive power project.