Illustrative image – not actual.West Bengal Power Devp. Corpn. (WBPDCL) is expected to commission the Unit V (250 MW) of Santaldih coal based power plant by end-December 2007. D Mukherjee, Dy-General Manager, currently, civil works told ProjectsToday that the project work is underway at full swing. Development Consultant Pvt. Ltd is the consultant and, Simplex Infrastructures and BHEL are the contractors for the Rs.1,300 crore project.
On completion of the Unit V, the Corporation plans to take up Unit VI with a similar capacity for implementation. The necessary environmental clearance from the Ministry of Environment and Forests (MoEF) has already been secured for the expansion.
Related Links:
Project profile