Sanghvi Movers has received work orders aggregating to Rs 150 crore from independent power producers (IPP) in the renewable energy sector, for providing crane rental services along with allied services.
This also comprises wind turbine generator (WTG) surface logistics, inter-carting, installation and pre-commissioning of WTGs, and development of a wind farm and a storage yard. Crane services account for approximately 50 percent of the total contract value, and the balance accounts for the activities under wind-based EPC services.
The contracts are of 18 months duration starting from April, 2023 and ending in October, 2024. Out of the total contract value, 41 percent of the value will be executed in FY24 and the balance will be completed in FY25.
The total order value translates to 539 MW of new capacity addition, with the new order win.