Illustrative image – not actual.
The grinding unit of Sanghi Cements, which is coming up at Kachchh in Gujarat, is expected to be commissioned in October 2002.
It may be recalled that the company had recently, commissioned its clinker unit. This unit has a capacity of 2.61 million tonnes. The entire project has cost the company more than Rs.1,000 crore.
The cement plant, when conceived was estimated to cost Rs.664 crore and was scheduled for commissioning in 1996-97. However, due to certain legal and environmental concerns the project was delayed, which in turn led to cost overruns.