The Bhilwara based Sangam Group has decided to foray into steel business through a new subsidiary Mahalaxmi TMT.

The company will set up an integrated steel plant near Wardha in Maharashtra in two phases. It will involve a capital expenditure of Rs 697.50 crore. The project is to be funded by an equity contribution of Rs 217.50 crore from the promoters while the remaining Rs 480 crore will be raised through debt. The company has already secured loans from a consortium of eight banks, led by Union Bank of India.

The plant is to have a capacity of 2.40 lakh tpa for mild steel billets in the first phase which will be completed by May 2011. Later the company plans to ramp it up to 3.36 lakh tpa by May 2012 in the second phase. It is also planning to set up a five lakh tpa capacity for manufacturing TMT bars, angles and channels capacity along with 40 MW captive power plant in the second phase.