Sandur Manganese & Iron Ores has successfully commissioned the 33 MW solar power plant at Kudligi taluk in Vijayanagara district of Karnataka. The company had signed a power purchase agreement (PDA), share subscription agreement (SSA) and shareholders agreement (SHA) with ReNew Green Energy Solutions.
The scope of work involved the construction of a 33 MW solar power plant and 3X3300 KW, 9.9 MW wind turbine generators, along with associated electrical equipment interconnecting the power with Karnataka Power Transmission Corporation (KPTCL).
Sandur Manganese & Iron Ores has achieved its objectives to procure power at a cheaper cost for operating all three existing furnaces of the ferro-alloy plant and other expansion activities at Vyasankere in Hosapete taluk, Vijayanagara.